Installation
The tube is fabricated to a size that, when installed, will tightly fit the internal circumference and the length of the original conduit. Allowances are made for circumferential stretching during inversion.
CIPP Liner is installed by licensed general contractors with extensive experience in all types of sewer rehab work. The installation crews, experienced in sewer rehab, are further trained on the fine points of cured in place liners by working "hands on" with crews experienced with CIPP Liner.
The line is prepared for the CIPP Liner by completing all necessary spot repairs, removal of any obstructions, and a thorough cleaning with high pressure water. The service on the line is maintained with by-pass pumping if required.
The tube is vacuum impregnated with resin (wet-out) under controlled conditions. The volume of resin used is sufficient to fill all voids in the tube, provide nominal thickness and diameter, plus allow for polymerization and migration into cracks and joints of the original pipe.
The tube, after wet-out, is placed in the existing pipe through an existing manhole (or other approved access point) by means of an inversion process and the application of hydrostatic head sufficient to fully extend it to the next designated manhole or termination point. The tube is inserted into a vertical inversion standpipe with the impermeable plastic membrane side out. At the lower end of the inversion standpipe, the tube is turned inside out and attached to the standpipe so that a leak proof seal is created. The inversion head is adjusted to be of sufficient height to cause the impregnated tube to invert from point of inversion to point of termination and hold the tube tight to the pipe wall, producing dimples at side connections.
Care is taken during the inversion so as not to over-stress the felt fiber. A lubricant is used to reduce friction during inversion. This lubricant is poured into the inversion water in the down tube or applied directly to the tube. The lubricant is a nontoxic, oil-based product that has no detrimental effects on the tube, boiler, or pump system.
After inversion is completed, a suitable heat source and water re-circulation equipment are used to circulate heated water throughout the pipe. The equipment is capable of delivering hot water throughout the section to uniformly raise the water temperature above the temperature required to effect a cure of the resin. The heat source is fitted with suitable monitors to gauge the temperature of the incoming and outgoing water supply. Another such gauge is placed between the impregnated tube and the pipe invert at the termination point to determine the temperatures during cure.
Initial cure will occur during temperature heat-up and is completed when exposed portions of the new pipe appear to be hard and sound and the remote temperature sensor indicates that the temperature is of a magnitude to realize an exotherm or cure in the resin. After initial cure is reached, the temperature is raised to the post-cure temperature. The post-cure temperature is held for a period, during which time the re-circulation of the water and cycling of the boiler to maintain the temperature continues.
The new pipe is cooled to a temperature below 100 degrees F (38 degrees C) before relieving the static head in the inversion standpipe. Cool-down is accomplished by the introduction of cool water into the inversion standpipe water being drained from a small hole made in the downstream end. Care is taken in the release of head so that a vacuum does not develop that could damage the newly installed pipe.
After the new pipe has been cured in place, the existing active service connections are reconnected from the interior of the pipeline by means of a television camera and a remote-control cutting device.
For more information see our
C.I.P.P. Corp. website.